rfreeman27 02-27-2005 08:34 PM

work maximer F2, they were a custom order wheel from japan, as far as I know there is one set in the us (me) and one in PR.



They are actually built by stern, but for some reason work rebadged them. I have the stern centercaps..



-bobby

Il RX8 lI 02-27-2005 10:16 PM

Hmm...any way to give a percentage of completion on this project?

djgiantrobot 02-28-2005 12:21 AM


Originally Posted by Il RX8 lI' date='Feb 27 2005, 08:15 PM
Hmm...any way to give a percentage of completion on this project?




knowing bobby, about 20% so far https://www.nopistons.com/forums/pub...#>/biggrin.png

rfreeman27 02-28-2005 10:05 AM

Well,



Now I am on MY schedule as far as working on the car is concerned. I still have a **** load of stuff to do, but I will work a lot faster then the fab guy does https://www.nopistons.com/forums/pub...IR#>/smile.png



I'd say it is at about 65% done. The fabrication was the major chunk of the work that needed to be finished.



The new PPF for the transmission still needs to be made, but that is "3 hours of work" according to kayo.



Here is the List of things to do:



Tear down motor and inspect

Order rebuild kit

order 10lbs wastegate springs from tial

port intake and exhaust

assemble motor

install motor

make s/s coolant lines (mabye)

Install r1 oil coolers+ s/s lines

GET THE TRANS! They are taking forever!

Cut the trans tunnel for the shifter

Take the car back to kayo's for the stainless steel torque arm

install driveshaft

tune...

NaughtyFD 02-28-2005 05:24 PM


Originally Posted by rfreeman27' date='Feb 28 2005, 08:05 AM
Well,



Now I am on MY schedule as far as working on the car is concerned. I still have a **** load of stuff to do, but I will work a lot faster then the fab guy does https://www.nopistons.com/forums/pub...IR#>/smile.png



I'd say it is at about 65% done. The fabrication was the major chunk of the work that needed to be finished.



The new PPF for the transmission still needs to be made, but that is "3 hours of work" according to kayo.



Here is the List of things to do:



Tear down motor and inspect

Order rebuild kit

order 10lbs wastegate springs from tial

port intake and exhaust

assemble motor

install motor

make s/s coolant lines (mabye)

Install r1 oil coolers+ s/s lines

GET THE TRANS! They are taking forever!

Cut the trans tunnel for the shifter

Take the car back to kayo's for the stainless steel torque arm

install driveshaft

tune...






So what trans are you using? The Jerico or the other?

rfreeman27 02-28-2005 09:50 PM

jerico

rfreeman27 03-02-2005 02:27 PM

Tore the motor down Yesterday.



I need new rotor bearings :(



but everything else looked cherry, should have it rebuild/ported by next week.



-bobby

knonfs 03-02-2005 07:09 PM


Originally Posted by rfreeman27' date='Mar 2 2005, 04:26 PM
Tore the motor down Yesterday.



I need new rotor bearings :(



but everything else looked cherry, should have it rebuild/ported by next week.



-bobby






Looking good, will love to se it personally once its done https://www.nopistons.com/forums/pub...1047683894.gif

rfreeman27 03-03-2005 03:57 PM

Thanks, where in MD do you live?

rfreeman27 03-04-2005 04:55 PM

This weekend:



Port housings/irons, paint irons, cleannn everything!